Cubic yards for a slab, footing or column — and the honest bag count, so you know when to stop bagging and call a truck.
Concrete needed
3.26cu yd
20 × 12 ft at 4 in, including 10% over-order
Quantities are rounded up, because materials are sold in whole units and a second trip costs more than a spare box. Cost figures are typical US ranges and are not a quote — always price against your own supplier.
45 bags of 80 lb, or 60 bags of 60 lb. That is the number that tells you bagging is the wrong choice for anything approaching a yard — a truck delivers better, more consistent concrete for less money and none of the mixing.
A 20 × 12 ft slab at 4 in thick is 80 cubic feet, or about 3.3 cubic yards with a 10% allowance. That is ready-mix territory — roughly 148 bags of 80 lb otherwise.
4 in for a patio or walkway on a compacted base. 5–6 in for a driveway, and 6 in with rebar if trucks or an RV will park on it. Base preparation matters more than the extra inch.